Installation of window

November 27, 2010

Advertisements

Concept images of 3rd floor

November 19, 2010

Living Room to East

Living Room to North


City Centre Library: not just books

November 17, 2010

“It’s going to be like no library you’ve ever seen,” Whalley branch manager says.
Click here to read the article featured in the Surrey/North Delta Leader.


Work is continuing on the roof

November 17, 2010

Work is continuing on the roof, framing, electrical and mechanical systems. The scaffolding is expected to come down at the end of next week.

Furniture request for proposal has been sent out.

Coffee shop will be announced soon.


The roof is currently being framed

November 3, 2010

The architects are finalizing the design for the green roof.

Other items for November include elevator installation, plumbing and HVAC systems, framing, and construction of the grand stairs.